Power problems in Tagachaguppe for Industries

Aug 26, 2022 | Updates | 0 comments

Dear All,

Following numerous complaints from industries in Tagachaguppe regarding the very poor service by BESCOM, KIA representatives organized a meeting on 26th May 2022 at Gardenia resort.
Plans and commitments being made by BESCOM during the last meeting with the k1 kengeri sub division by SE (West) and other senior officers on 17th May were explained to all present.

There is also a delay in changeover to the 220Kv line from Bidadi and the need for coordination between KPTCL and BESCOM to get it executed immediately.

They also need to work on their future assignments in the next couple of months to provide quality service by changing under capacity transformers along with laying of UG cables and connecting them to new feeders.

Many thanks to Mr. Rahul Kanoria(KIA MC Member and Mr. Abhijeet M/s N P Industries for organising the programme in such a short time.